Al Estiqlal Residential Buildings  
The Client M/s Al Khaleej Development Co.
The Consultant M/s Ghareeb Engineering
Contract Amount BHD709, 738.000 – Bahrain Dinars Seven Hundred Nine Thousand and Seven Hundred Thirty Eight Only.
Contract Duration 18 Months
Commencement Date March 01, 2012
Completion Date September 15, 2013

Project Overview
The Tameer Commercial District is located on the industrious Al Istiqlal Avenue. The area includes showrooms, commercial buildings, and lands. Two twin high rise towers have already been constructed, as well as six showrooms.

The 3rd tower is a 9 storey building; works include construction, development of basement parking, a recreational floor at the 7th level, and all associated electro-mechanical works and external services

The contract scope of work covers substructure works, superstructure works, MEP Works and external associated services and car parks works.

The substructure works including excavation, filling, footings concrete, ground slab concrete & waterproofing of the underground water tank, lift pit and foundations.
The Superstructure works including the Concrete frame structure and block works for the Ground floor, Typical Floor (06 Nos.), Recreation floor and Roof works with roof water proofing works and external finishing works. The works include the construction of the Electrical Sub Stations attached to the building as per the contract drawings.
External works cover the Car parks at Ground Floor level, septic tank and car parks at front set back.

   

 